Name of the work

 

Water supply improvement works - transmission main from peechi dam to chembukkavu reservoir.

 

Description

 

Pipe Laying- 18.75 km from Peechi dam to Chembookkavu Reservoir.

 

Filter Plant- Renovation of Chemical house, flocculator and clariflocculator, Filter bed, Raw water pumping station, Back water wash pump, Air blower, Chlorinator, Flash mixer, Aerator and treatment unit.

Pipe carrying bridge 4 Nos

 

Magnetic type water meter chamber and clorinator room Providing Bulk metre and chlorinator room.

 

Contract Amount

42,18,18,118

Awarded Date

25-02-09

Awarded To

IVRCL Infrastructures

Expected Date of Completion

11-09-2010

Physical Status

30%

Financial Status

29 %

Contact Person

K.K.Vasudevan, Technical Officer (WS&S)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 