Water Supply -package 2
Work Progress as on 30 April 2012
The 32nd Empowered committee approved to award the work after negotiation by the evaluation committee (Subject to the approval of ADB for Negotiation). The tender will be submitted to the three members committee to furnish their opinion within twenty days. With the opinion of the three members committee if needed the tender will be submitted to council of Ministers for final decision with recommendation of council of corporation.
Last Updated (Monday, 07 May 2012 06:57)